The project required a 1km x 1km island to be dredged from the sea and the construction of industrial equipment bases. The project all required plant procurement, shipping and erection and construction of ancillary buildings, generator plant, desalination plant and a loading/unloading yard and jetty capable of producing and handling 3 million tonnes of iron ore per annum.
?>